8.10.2024

Tankkari 3 doors

The installation of the external and interior doors of Tankkari 3 will start in week 41/2024, on Monday 07.10.2024 at 8 a.m. Contractor Pihla Group Oy.

The installers will notify you by apartment-specific notices approximately 2-3 days before the renovation work starts in your apartment.

The total duration of the renovation will be approximately five weeks. The changing of the doors will be started from the fourth floor, and they will move down from there.

4th floor starting 7th of October

3rd floor starting 14th of October

2nd floor starting 21st of October

1st floor starting 28th of October

The times are directional

Locks in all rooms will be changed. Keys will be handed over only against identification at our office at Kustaa Aadolfin katu 1. The keys can be picked up from the 1st of October. Notice that the office is closed during the autumn break (14.-18.10.2024)

Preparatory instructions

The security lock should be left open for the days of installation.

For questions regarding the renovation, please contact the office of Kiinteistö Oy Tankkari or the contractor